5-18-22
Hill Farm Road is paved leading up to the Hill Farm Condominiums building! Another major milestone will be completed next week when the foundation is done; currently, the foundation is 75% finished with the first of two elevator cores being framed in. After the foundation is wrapped up, the bearing points will be poured and then the concrete planks for the garage ceiling/main floor will be installed!