Whether you are a future Hill Farm Condominium homeowner, a neighbor, or just curious, our goal is to keep you updated on our construction process! Every month (& sometimes more!) we send out an email newsletter with the newest construction information. By joining our email list, you will get all updates, images, and videos directly in your inbox.





June Drone Video!

6-16-23

The first floor’s sheetrock is all finished now! The rest of this month will include the second floor getting painted and the final cabinets going in the third-floor condos.

June Drone Shots!

6-2-23

The third floor was fully sheetrocked in the Spring, and now it’s fully painted! Next, we’ll see cabinets going in all third-floor condos.

May Drone Video!

5-19-23

The third floor is now all tapped and mudded including that floor’s beautiful vaulted ceilings! Work is continuing on the first floor’s sheetrocking.

May Drone Shots!

5-1-23

The second floor was fully sheetrocked in April, and the large Club Room and Lobby windows went in. This month the first floor will be sheetrocked!

April Construction Update!

4-21-23

April has been a busy month with sheetrocking the second floor and finishing windows throughout the building including the stunning, large windows in the Club Room and Lobby!

March 2023 Construction Update Video

3-30-23

Watch our second construction update as Jim Seabold takes you along on the journey of building this beautiful addition to the North Oaks community.